How the concrete calculator works
For a slab or strip footing, multiply length × width × depth. Depth is in millimetres, so divide it by 1,000 first. A 6 m × 3 m slab at 100 mm is 6 × 3 × 0.1 = 1.8 m³.
For round post holes it's π × radius² × depth for each hole, times the number of holes. A 300 mm hole 600 mm deep holds about 0.042 m³, so eight of them take about 0.34 m³.
Then add a margin for waste. 5 to 10% is normal for a slab on a flat, well-prepared base. Go to 15% on uneven ground, for footings dug by hand, or when the formwork isn't dead square.
Bags or ready-mix?
A 20 kg bag of premix makes roughly 0.009 to 0.01 m³ once mixed, which is why you need about 108 bags for a cubic metre. Check the yield on the bag you're buying, because it varies by brand and mix.
Bags make sense for post holes, small pads and patch-ups. Past about half a cubic metre you're mixing a lot by hand, and over 1.5 m³ a ready-mix truck is nearly always cheaper and quicker. Suppliers usually deliver in steps of 0.2 m³ and many charge a short-load fee for small orders, so ask when you book.
Common slab depths
| Job | Typical depth |
|---|---|
| Garden path or shed slab | 75–100 mm |
| Patio or house slab (non-structural areas) | 100 mm |
| Driveway for cars | 100–125 mm |
| Heavier vehicles | 150 mm or more |
These are common starting points, not engineering advice. Follow your engineer's drawings, your council's rules and the relevant Australian Standards for anything structural.