Concrete calculator

Work out how much concrete you need for a slab, strip footing or post holes, in cubic metres and 20 kg bags.

What are you pouring?
m
m
mm
Add extra for waste and spillage
Concrete needed–
Or in 20 kg bags–About 108 bags of premix per m³
Add to a quote

How the concrete calculator works

For a slab or strip footing, multiply length × width × depth. Depth is in millimetres, so divide it by 1,000 first. A 6 m × 3 m slab at 100 mm is 6 × 3 × 0.1 = 1.8 m³.

For round post holes it's π × radius² × depth for each hole, times the number of holes. A 300 mm hole 600 mm deep holds about 0.042 m³, so eight of them take about 0.34 m³.

Then add a margin for waste. 5 to 10% is normal for a slab on a flat, well-prepared base. Go to 15% on uneven ground, for footings dug by hand, or when the formwork isn't dead square.

Bags or ready-mix?

A 20 kg bag of premix makes roughly 0.009 to 0.01 m³ once mixed, which is why you need about 108 bags for a cubic metre. Check the yield on the bag you're buying, because it varies by brand and mix.

Bags make sense for post holes, small pads and patch-ups. Past about half a cubic metre you're mixing a lot by hand, and over 1.5 m³ a ready-mix truck is nearly always cheaper and quicker. Suppliers usually deliver in steps of 0.2 m³ and many charge a short-load fee for small orders, so ask when you book.

Common slab depths

JobTypical depth
Garden path or shed slab75–100 mm
Patio or house slab (non-structural areas)100 mm
Driveway for cars100–125 mm
Heavier vehicles150 mm or more

These are common starting points, not engineering advice. Follow your engineer's drawings, your council's rules and the relevant Australian Standards for anything structural.